|
Corporate
Profile
Perusahaan
Perseroan (Persero) PT Aneka Tambang Tbk (Aneka
Tambang or the "Company"), is a leading
Indonesian mining and minerals processing company.
Aneka Tambang's core businesses are vertically
integrated from exploration and mining through to
processing, marketing, and trading of nickel and
gold. Other products include bauxite and iron sand.
The Company also enjoys significant competencies in
providing geological and exploration services to
third parties. Aneka Tambang was established on July
5th, 1968 following the merger of 7 state owned
companies. Aneka Tambang was partially privatized in
1997 and its shares are listed on the Jakarta Stock
Exchange (JSX) and Surabaya Stock Exchange (SSX).
The partial privatization raised capital needed for
expansion of production facilities. Privatization is
further proof of Aneka Tambang's commitment to
become a world class company.
Significan events
1997April
28
The
Contract of Work (COW) of Gosowong Gold Project,
Halmahera Island was signed by the Government. The
project is a joint venture between Aneka Tambang and
Newcrest Singapore Holdings Pte., Ltd.
June
25
Dwadown
of the Gold Project Facility by Aneka Tambang of
135,764.5 oz from the 160,000 oz facility. This
facility represented the first gold loan ever
extended to an Indonesian mining company.
July
24
Technical
consultancy agreement relating to the installation
of a chlorination process in Logam Mulia Smelting
and Refinery was signed with Western Australia Mint
Company.
July
30
Aneka
Tambang acquired a 82 per cent., interest in the
issued share capital of ERI Ventures Inc., ("ERI"),
an exploration mining co., listed on the Vancouver
Stock Exchange in Canada.
August
7
The
signing of a memorandum of understanding with
Japanese Smelting companies, Pacific Metal Co.,
Ltd., Sumitomo Metal Mining Co., Ltd., and Nippon
Yakin Kogya Co., Ltd., to incrase high grade nickel
ore export from Gebe from 600,000 wmt to 850,000 wmt
over a period of eight years.
September
1
Completion
of a full environmental audit of the Company's
operation and implementation of a new environmental
plan by Aneka Tambang.
September
3
IMC
Mackay & Schnellmann, independent consultant,
completed the review of the Companys major
operations and key project, especially its mineral
reserves.
November
27
Partial
privatisation of the company through the sale of
430,769,000 new shares to the public representing
approcimately thirty five percent of the enlarged
issued share capital of the company and listing on
Jakarta Stock Exchange and Surabaya Stock Exchange.
November
30
Completion
of the development of Pongkor Plant II increasing
annual gold production at Pongkor from 2 tonnes to 5
tonnes (4 tonnes in 1998).
December
31
Completion
of the reevalution reserves at Gag Island Nickel
Project, Iran Jaya. The CoW approval is in process.
The project is a joint venture between Aneka Tambang
and BHP Asia Pacific Nickel Pty., Ltd.
December
31
Completion
of the basic design of FeNi III. The constuction
tender of the project will be conducted in 1998.
December
31
Completion
of the improvement program in securing gold product
in Pongkor Gold Plant and Logam Mulia Smelting and
Refinery by modifying standard operating procedures
and rearrangement of the plant layout.
Company's
Vision
- To be a wold-class
company and the leader in the Indonesian Mining
Industry
- To be and
efficient producer delivering value added
products and services
Company's
Mission
- To provide
superior products in core commodities nickel and
gold.
- To achieve
competitive advantage within the global market
place, through capitalization on core
competency.
- To be a profit
oriented company contributing to maximasion of
value for all stockholders.
- To enchance the
quality and prouctivity of human resources.
- To uphold the
corporate social responsilities for the welfare
of the community.
Message From the
Board of Commissioners
During
1997 Aneka Tambang moved closer to realising its
goal of becoming a world-class company and the
leader of the Indonesian mining industry. This was
demonstrated by strong performance of the Company
during the year.Despite the economic turbulence of
1997, which caused the depreciation of the Rupiah
against US dollar, Aneka Tambang was able not only
to achieve its production and sales targets for the
year, but also to accomplish its business plan. The
acquisition of the Gold Project Facility and the
oversubscription of Aneka Tambang's IPO shares,
indicate the Company's prominence within
international capital markets.As the mining industry
around the world experienced a general decrease in
metals and commodities prices; Aneka Tambang
responded effectively by positioning itself to limit
the impact of this price decrease through focusing
on improving productivity and efficiency.The Board
of Commissioners is confident thatAneka Tambang can
compete successfully in an era of increasing globalize
competition. With low cost of production,
significant high quality reserves, appropriate
social and environmenta/ concerns and a wealth of
experience in the industry, the Company will be able
to successfully compete with its international peers
and continue to grow its business. The Company's
achievements are the result of the efforts and hard
work of the directors, employees, and other
stakeholders. Therefore, we would like to convey our
gratitude and thanks. We our confident that Aneka
Tambang can maintain and improve its performance in
the years to come.
Jakarta
March 30, 1998.
The
year 1997 was a turning point in the 29 year history
ofAneka Tambang as Indonesia's leading mining
company completed the necessary steps leading to its
conversion to a publicly listed company. The public
offering process of Aneka Tambang was successfully
completed amidst the economic turmoil besieging
Indonesia in mid 1997. Undertaken during a period
when market forces were adversely inclined to any
major stock offerings, the oversubcription and aher
market performance of the Company's shares on the
exchanges underscored the trust and confidence of
the Indonesian and international investing public in
Aneka Tambang.Operational Performance:During
1997, the Company's production and sales volumes
showed satisfying results, where almost all
production targets were accomplished. Moreover,
exploration and development programs conducted by
the Company either independently or in joint
ventures with its partners, show further promising
prospects.Completion of a gold loan facility from
the syndication of Eve international banks, further
proved the Company's strong fundamentals.Financial
PerformanceThrough increase profitability, Aneka
Tambang fortified its financial performance in the
Indonesian mining industry, in an environment of
increased domestic and international
competition.With gross profits of Rp 197.27 billion
in 1997, the Company's net income of Rp 69.52
billion more than doubled over the previous year's
level of Rp 32.62 billion. Mineral exports accounted
for 79 per cent. and domestic sales comprised 21 per
cent. Of the total sales.
As of
year-end 1997, the total assets of Aneka Tambang,
including its subsidiaries, amounted to Rp 1,600.79
billion, an increase of some Rp 877.55 billion
Including Rp 561.70 billion from the IPO) compared
to the previous year of Rp 723.24 billion.
Growth
and DevelopmentBasic
design of FeNi lit plant has completed. Wherein, the
construction tender of the plant will be conducted
in the 1998. FeNi lit will increase production of
nickel in ferronickel from 11,000 tonnes Ni to
24,000 tonnes Ni per annum.Another project which
will further add growth is the Pongkor Plant II
expansion. This project will allow an increase in
gold production up to 5 tonnes per annum compared to
the current level of 2 tonnes.A joint venture with
Newcrest Singapore Holdings Pte. Ltd. in connection
with the development of the gold project atGosowong,
is another potentialsource of Company's future
growth.The Company's involvement with the oint
venture projects with major international and
Indonesian mining companies will help the Company
improve its skills and enable it to explore more
effectively mineral deposits in Indonesia.PrivatisationIn
November 1997, the Company :completed its Initial
Public Offering (IPO) with par value of Rp
500/share, sold at market share price of Rp 1,400.
The Company floated 430,769,000 B class shares
representing 35 per cent. of the enlarged capital.
The capital raising generated net proceeds of Rp
561:70 billion, strengthening the Company's
financial health, and partially financing the
company's future growth plan.
Strategy
Aneka
Tambang has continually expanded the scopp:of its
operations to strive to become a world class miner.
The Company has set its strategy by maintaining
focus on nickel and gold production.To support its
growth, the Company has also undertaken a strategy
to increase the exploration activities on 73
properties including 1 Contract of Work, covering an
area of 5.3 million ha.Furthermore, to improve its
competitive advantages, the Company has undertaken a
strategy to capitalised on joint venture
arrangements with leading international mining
companies such as BHP, QNI, Aberfoyle, Ashton, and
Newcrest.
To
help meet the competitive challenges of the future,
the Company will restructure its business into four
primary divisions to enhance transparancy, increase
divisional accountability and assist Aneka Tambang
to meet future challenges.
Environmental
Concerns
Aneka
Tambang's environmental concerns during the year
have been exhibited through adopting a new
comprehensive environmental policy for
implementation.
Business
Prospects and Risks
The
outlook for gold and nickel in 1998 will depend on
three factors: the price elasticity of mine supply,
the role of the official sector, and the prospects
for physical demand. Nickel and gold prices face a
relatively weak position in the near term, despite
good demand. This situation is caused by an
oversupply, weakening Asian jewelry demand and
competition from stainless steel industry.Because of
the sharp depreciation of the Rupiah against the US
dollar, Company Sales have increased since its core
products of nickel and gold are sold in US dollars.
This increase was partially offset by lower prices
for nicker and gold. In addition, a large portion of
operational expenses are incurred in Rupiah. These
advantages enhanced the Company's profitability in
1997.In 1997, EastAsian Economies represented over
one third of demand for Aneka Tambang's products.
Although conceptually the structural weakening of
these economies may represent added demand risk for
the company's products, management is confident that
any such added risk can be mitigated. This is
primarily due to ferronickel's positioning and
segmentation that it has achieved within the overall
nickel market, where the product is in high demand
by all of its customers; enabling the company to
ship supply quickly, should the need arise.closing,
the Board of Directors wishes to express its thanks
to all shareholders, business partners and the Board
of Commissioners for their continued support, and
also to all employees for their dedication, hard
work and commitment which has made this year, 1997,
such an important one for the company.Jakarta, March
30, 1998
OPERATIONAL
REVIEW
Aneka
Tambang’s main operations are vertically
integrated from exploration and mining through to
processing , marketing and trading of nickel and
gold deposits in Indonesia. Besides those core
commodities, bauxites and iron sand are also mined.
Aneka Tambang also has a number of significant
exploration and development projects either
wholly-owned or in joint ventures with major
international mining companies such as BHP, QNI,
Aberfoyle, Newcrest and Ashton.
CORE PRODUCTS
Nickel Ore
Background
The
Company has three active Lateritic Nickel mines, at
Pomalaa, Gebe and Gee Islands. Pomalaa mined is
divided into three areas, northern, middle and
southern, covering an area of about 7,589 ha.
Pomalaa is the centre of the Company’s nickel
operations and the location of its ferronickel
smelter.
Discovery
of nickel in Pomalaa, South East Sulawesi, was
reported first in 1909. Nickel exploration
commencedin 1934 and production started in 1939,
reaching significant level in 1962.
The
mine in Gebe Island, covering an area of about 1,225
ha., was established by Aneka Tambang in 1978.
Production was commenced in 1979. Aneka Tambang is
in the process of developing a new loading facility
at Gebe which will be completed at the end of 1998.
The
mine at Gee Island commenced its operation in
November 199, and the first production was sent to
Pomalaa smelter in December 1997. Mining is carried
out through outsourcing, using PT Minerina Bakti, as
the contractor. The afore-mentioned nickel mines
reserve a huge amount of Saprolitic ore and
Limonitic ore.
Production
At
Pomalaa, nickel ore is mined using an open pit
mining technique. Pomalaa produced 706,509 wmt of
Saprolitic ore in 1997. Approximately 330,975 wmt of
this ore was processed at the ferronickel plant,
while the remaining ore, 375,534 wmt was exported to
Japan. For 1998, Aneka Tambang expects production to
be around 555,000 wmt, of which 300,000 wmt is for
exports and 225,000 wmt is for feedstock of the
ferronickel smelter.
Gebe
produced 2,124,877 wmt of nickel ore during 1997, of
which 1,223,663 wmt was Saprolitic ore and 1,011,214
wmt was Limonitic ore. In 1997, export of Saproltic
ore to Japan was 866,713 wmt, while export of
Limonitic ore to Queensland Nickel (QNI) in
Australia was 1,207,681 wmt. The remaining 281,776
wmt of Saprolitic ore in 1997, was used as feedstock
for the smelter. In 1998, the Company expects
production at this mine to reach 2,000,000 wmt of
Saprolitic and Limonitic ore. Of this production,
the Company will export 880,000 wmt of ore to Japan,
1,000,000 wmt of ore to Australia, and 120,000 wmt
of ore wil be supplied to Pomalaa smelter.
In
its first month of operation in December 1997, the
mine at Gee Island produced 9,133 wmt of nickel ore.
The mine is expected to produce about 400,000 wmt of
nickel ore anually for the next 10 years, starting
in 1998.
As
ore reserves decline at Pomalaa, Gee and Halmahera
Island will replace the ore supply from Pomalaa to
the smelter.
Ferronickel
Background
The
construction of Pomalaa smelter commenced in 1973,
commissioning in 1975. Commercial operation started
in 1976, producing ferronickel from Pomalaa and Gebe
ore. The smelter produced high and low carbon
ferronickel, in the form of shot or ingot.
FeNi
I smelter line has an annual capacity of 5,500
tonnes nickel in ferroickel. To increas the
production, Aneka Tambang expanded FeNi II smelter
line in 1995, doubling the production capacity of
ferronickel.
The
Company plans to build a third ferronickel smelter
line, FeNi III, which will produce 13,000 tonnes
nickel in ferronickel and increase the Company’s
annual ferronickel production capacity to 24,000
tonnes nickel in ferronickel. Basic design was
completed in December 1997, and the construction
tender will be conducted in 1998. FeNi III is
expected to start commercial operation by 2001 and
will primarily utilise ore from Halmahera Island.
As
part of the expansion, the Company proposes to
change from oil-fired power generation to a 2 x 55
MW coal-fired power plant, pursuant to a memorandum
of Understanding between Aneka Tambang and PT
Suvarna Bumi Persada, signed on July 2nd
, 1997. The agreement stipulate a 13-year power
supply agreement at a total cost not to exceed US$
0.055 per kwh. Resulted to lower cash cost of
ferronickel in 1997 amounting to US$ 1.79 per pound.
The
Company’s Pomalaa ferronickel smelter facilities
includes a power plant, a laboratory for analysing
nickel ore and ferronickel samples, workshops for
the maintenance of mining and plant equipment, and
dockyard for ship maintenance and repairs.
The
Pomalaa ferronikel smelter attained ISO 9002
certificate on April 3rd, 1996 attesting
to the quality and management of the smelter. The
quality certification includes the processing and
distribution of ferronickel, laboratory, equipment
maintenance, material purchase, health and safety,
recruitment of new employees, and training programs.
The certificate will be audited every six months,
the next audit will be in April 1998. Audit results
for 1997 (April and October) were satisfactory. This
certification represented part of the Company’s
attemt to create a niche within the overall nickel
market.
Production
In
1997, Pomalaa smelter produced 9,999 tonnes of
ferronickel (9,553 tonne in 1996). Nickel ore supply
came from Pomalaa and Gebe. However, the 1998
projection shows that the ferronickel production
will be approximately 8,350 tonnes. Production will
decline because of the smelter replacement and
modernisation (FeNi I), which will commence in
August 1998. By February 1999, Aneka Tambang plans
to switch on the replaced and modernised FeNi I.
Production is projected to reach its full capacity
by April 1999.
Development
Program
Aneka
Tambang has a strong development progra for its
nickel operations mines which includes the potential
future development of nickel resources of Gag Island
(joint venture with BHP), Weda Bay (joint venture
with Strand), and at Halmahera Island (letter of
intent with QNI).
The
relationship between Aneka Tambang and BHP Asia
Pacific Pty.Ltd. was formalised into a mining joint
venture connection with the nickel deposits at Gag
Island, Irian Jaya. The Gag Nickel project is 25
percent owned by Aneka Tambang and 75 percent owned
by BHP. Completion of project fesibility study will
depend on the approval of the Contract of Work and
the establishment demonstration plant. Currently,
the project is in the drilling program, ore
preparation test and sample collection, and
environmentally analysis stages. The first phase of
the production is expected to commence around 2003,
producing 30,000 tonnes of nickel and 2,700 tonnes
of cobalt per annum. The development project at Gag
includes a nickel refining plan as well as mining.
In
August 1997, the Company commenced exploration of
nickel deposits at Weda Bay, Halmahera Island which
covers an area of approximately 120,500 ha. This
program is a joint venture between Aneka Tambang (10
%) and Strand Management Ltd. (90 %), wherein, Aneka
Tambang has an option to increase its holding to a
25 percent interest. At the end of December 1997, an
inferred resource of 50 million dry tonnes of ore at
a grade of 1.51 percent nickel had been identified.
Aneka
Tambang signed a letter of intent with Queensland
Nickel (QNI) in June 1996 regarding Limonitic nickel
ore deposits at Halmahera Island (Tanjung Buli and
Pakal Island), and Obi Island. In April 1997, the
first phase of a scoping study for the project was
completed by Fluor Daniel SA Pty.Ltd. The second
phase is expected to be completed by April 1998, The
nickel deposits amounting to 30,000,000 wmt of ore
will be used as Saprolitic feed for the Pomalaa FeNi
III smelter expansion.
Gold
and Silver
Background
Aneka
Tambang operates a gold and silver mine at Pongkor,
West Java, covering an area of 4,058 ha. Aneka
Tambang discovered the Pongkor gold deposits in
1988, the plant was constructed in 1993 and
commercial production commenced in May 1994. In
November 1997, the construction of the expansion at
Pongkor was completed to 5 tonnes capacity.
Reserves
As of
June 30th , 1997, based on evaluation
from IMC Mackay & Schnellmann, an independent
consultant, the proven and probable reserves at
Pongkor, West Java were estimated to be 6,304,600
wmt with average recoverable grades of 11.6 g/t gold
and 124.1 g/t of silver.
Production
A
conventional cut and fill stopping mining technique
is used to mine veins of gold at Pongkor. In 1997,
Pongkor mine produced 2,004 kg of gold (1,827 kg in
1996) with the average of grade of 11.6 g/t and
15,530 kg of silver (14,732 kg in 1996) with the
average ore grade of 180.40 g/t. Completion of
Pongkor Plant II will result in the producton of
4,044 kg of gold and 22,702 kg of silver in 1998.
Development
Program
Exploration
funding for gold and silver is undertaken by Aneka
Tambang either independently or in joint ventures
with domestic or international partners.
The
company has a number of joint venture arrangements
with international partners in respect of its gold
exploration. There are 17 applications of the
Seventh Generation of Contract of work, which will
be granted in 1998.
On
March 17th, 1997, the President of the
Republic of Indonesia approved the Sixth Generation
of Contract of Work between the Indonesian
Government and PT Nusa Halmahera Minerals, a company
incorporated in Indonesia and owned by Aneka Tambang
(10 %) and Newcrest Singapore Holdings Pte.Ltd. (90
%), regarding the gold project in Gosowong. Aneka
Tambang has an option to increase its holding to a
17.5 percent interest, after the completion of the
feasibility study. Current status indicates that the
Gosowong site work will commence in early 1999,
producing approximately 160,000 oz of gold per
annum.
On
July 23rd, 1997, a joint venture
agreement was signed between Aneka Tambang (25 %)
and Aberfoyle Pungkut Investments (75 %), for gold
prospect at Kotanopan and Pagar Gunung, North
Sumatera. Aneka Tambang has an option to increase
its interest to 40 percent. At the end of 1997, the
project is at a regional stream sediments sampling
to define new drill targets over areas with
anomalous copper and gold.
Aneka
Tambang also has a joint venture with Aberfoyle
Indonesia Investmens Pte,Ltd. for the gold prospect
at Nusa Tenggara Timur and Nusa Tenggara Barat.
Aneka Tambang owns a 20 percent interest, while
Aberfoyle Indonesia holds 80 percent interest. At
the end of 1997, project priorities are to follow up
a large number of gold geochemical anomalies in
Western Flores to identify prospects with potential
for epithermal style gold mineralisation. Detailed
exploration will be set based on the evaluation
results from regional aeromagnetic surveys.
Another
join venture of Aneka Tambang is with Western Mining
Corporation in connection with the gold prospect in
Solok, West Sumatera. Aneka Tambang holds 20 percent
with the option to increase its interest to 30
percent, while Western Mining holds the balance. At
the end of 1997, the project was still at general
survey stage.
Aneka
Tambang also has an interest in Antam Resource
International Limited (ARI), an exploration company
listed on the Vancouver Stock Exchange, which
focuses on gold exploration in 11 KP’s such as in
Cikidang, Cibaliung and Trenggalek block C,D and E.
One
of Aneka Tambang’s promising gold deposits is at
Cibugis, west of Bogor, with indicated resources of
high grade gold ore of about 552,541 tonnes with a
gold content of 6,23 g/t (cut of grade 4 g/t gold)
or inferred resources of low grade gold or of about
10,000,000 tonnes with a gold content of 2.61 g/t
(cut of grade 0.5 g/t). The current status of the
project is at feasibility study and environmental
analysis stages.
At
Trenggalek, East Java, block A and B, Aneka Tambang
has a joint venture with PT Fajar Mineralalami
International. The joint venture has identified 7
blocks of gold prospects, containing0.2 to 9,91 g/t
of gold. Aneka Tambang owns a 50 percent interest
with an option to increase its holding by 10
percent. The current status of the project is
detailed mapping, trenching, geophysics, rock and
grid soil samppling, topography surveying,
drillingand sample analysis.
Logam
Mulia Smelting and Refinery
Aneka
Tambang owns and operates Logam Mulia Smelting and
Refinery at Pulo Gadung, eastern Jakarta, which was
constructed in 1979. Logam Mulia Smelting and
Refinery is the only precious metal refinery in
Indonesia and therefore, all non-copper based
bullion produced in Indonesia, as well as recyclcled
scrap gold, silver and platinum is refined in Logam
Mulia.
In
1997, Logam Mulia refined 30,772 kg of gold and
170,913 kg of silver produced by Aneka Tambang and
other mining companies.
In
order to increase the efficiency of Logam Mulia
refinery, the Company is conducting studies to
improve the refining process. To complement Logam
Mulia’s strong local brand positioning on the
international scene, the company is also pursuing
London Bullion Market Association (LBMA)
accreditation.
NON
CORE PRODUCTS
Bauxite
Background
The
Company has a bauxite mine in Kijang, Bintan Island,
province of Riau, covering an area of 8,002.4 ha.
Discovery of bauxite was first reported in 1924 on
Bintan Island, from which bauxite has been mined and
exported since 1935.
Reserves
Based
on the evaluation from IMC Mackay & Schnellmann,
an independent consultant, the remaining reserves as
of June 30th,1997, were 964,900 wmt.
Aneka Tambang has identified an area of probable
bauxite reserves at Wacopek with indicated resources
of about 2,773,600 wmt.
Production
In
1997, stated production of 808,749 wmt was produced
from two areas: Pari and Galang. The production of
bauxite in 1998 is projected to be 850,000 wmt. The
Wacopek mine is expected to start producing in May
1998, replacing bauxite production from Galang and
Pari.
Development
Program
The
Kijang mine is forecast to reach the end of its
reserves in 2001. Aneka Tambang is reviewing the
possibility of developing in joint venture its other
mining development at Tayan, West Kalimantan, which
covers area of 21.120 ha and at Munggu Pasir, which
covers area of 15,280 ha. Mineral resources were
estimated to be 66 million tonnes of bauxite at
Tayan and 46 million tonnes at Munggu Pasir based on
temporary evaluation. The project still on the
feasibility study stage which will be completed in
1998.
Iron
Sand
Background
The
Company has two iron sand mining operations in
central Java, one at Cilacap and the other at
Kutoarjo. The Cilacap iron sand operation commenced
in 1971, while Kutoarjo in 1989.
Reserves
Based
on the evaluation from IMC Mackay & Schnelmann,
an independent consultant, the proven and probable
reserves as of June 30th, 1997 at Cilacap
mine were 2,655,236 wmt and at Kutoarjo 2,971,175
wmt. Aneka Tambang has also identified iron sand
reserves in Cipatujah, Tasikmalaya, amounting to
1,479,932 wmt and in Lumajang, amounting to
1,410,008 wmt.
Production
Iron
sand production in 1997 from Cilacap mine was
249,024 wmt and from Kutoarjo mine was 238,354 wmt.
For 1998, iron sand production is targeted to be
480,000 wmt from Cilacap and Kutoarjo and 178,000
wmt from Cipatujah and Lumajang.
Development
Program
Aneka
Tambang is undertaking new iron sand explorations at
Cipatujah, West Java, covering an area of 1,490 ha
and Lumajang, East Java, covering an area of 814 ha.
The feasibility study and an environmental analysis
of Cipatujah and Lumajang will be completed in 1998.
Diamonds
The
company has a joint venture with Ashton-Malaysian
Mining Company in connection with the exploration of
alluvial diamond deposits in Martapura, cempaka and
Danau Seran in South Kalimantan. Aneka Tambang holds
a 20 percent interest with the option to insrease
its holding to a 30 percent after the completion of
the feasibility sudy. The channels are estimated to
contain some 260 million cubic meters of diamond –
bearing dredgeable gravel – resources, with high
quality gem diamonds.
A
trial mining project has been designed to confirm
diamonds grades and recover diamonds for valuation
and sale. In 1997, the construction of dredging
equipment which has a capacity of 2.5 million cubic
meters per annum was completed. The dredge is
expected to be ready for commissioning at the end of
1998. If the results of the first stage of the
commercial production are favorable, the production
capacity will increase to 5 million cubic meters per
annum.
Copper
Aneka
Tambang has a joint venture with Ingold Holdings
Indonesia Inc., a wholly owned subsidiary of Inco
Limited, to develop copper resources in Maluku (on
the islands of Haruku, Ambin, Nusa Laut and Saparua).
The Company owns a 15 percent interest. Work
conducted in late 1997 identified the work site as
one with material occurences that tend to be copper
rich with high copper values in stream sediment
samples.
Geology
Unit
The
Geology Unit provides exploration services
(geological exploration, geophysical investigation,
surveying, drilling, chemical analysis and
electronic data processing) to Anke Tambang as well
as other third parties.
In
1998, the Geology Unit will focus on exploration of
new areas and existing KP’s, especially for the
core commodities, nickel and gold.
MARKETING
REVIEW
All
of Aneka Tambang’s sales are conducted
independently, through representative office in
Japan, or the selling agentin Switzerland which is
responsible for ferronickel salas in Europe and
South Africa.
Aneka
Tambang bases the prices of its commodities on
international metal prices, as quoted by the London
Metals Exchange (LME) and London Metal Bullion
Association (LBMA).
The
economic crises affecting Asia as of mid 1997 has
decreased demand for stainless steel, while entry of
new capacity has increased supply. Thus, nickel
prices have been on a download trend.
Total
sales in 1997 amounted to Rp 449.56 billion. Exports
contributed 79 percent of total sales and 21 percent
were generated from domestic customers, while
pricing of over 95 percent of sales was US dollar
driven.
CORE
PRODUCTS
Nickel
Ore
Nickel
ore revenues increased to Rp 111.26 billion, a 33
percent addition over 1996 level. The two
contributing factors were increased sales volume and
depreciation of rupiah. Sales volume of high grade
nickel ore increase from 1,102,601 wmt in 1996 to
1,242,247 wmt in 1997 due to higher Japanese demand.
The sales volume for low grade nickel ore also
increased from 995,334 wmt in 1996 to 1,207,681 wmt
to 1997.
Aneka
Tambang has established a strategic presence in
Asia, Europe and Australia. Japan is considered the
traditional market for the Company’s Saprolitic
ore due to high quality standards. Pacific Metal
Co.Ltd., Sumitomo Metal Mining Co.Ltd, and Nippon
Yakin Kogyo Co.Ltd. are the major buyers of
Saprolitic ore while the buyer of Limonitic ore is
Queensland Nickel Pty.Ltd., from Australia.
The
Company’s marketing strategy is to substantially
increase nickel ore sales through long term
contracts, surrently ranging from one year to three
years. As a result, on August 7th, 1997,
a memorandum of understanding for a longer term
sales contract was signed with the Japanese
Smelters, Sumitomo Metal Mining Co.Ltd., Nippon
Yakin Kogyo Co.Ltd., and Pacific Metal Co.Ltd.
Ferronickel
Ferronickel
which is used to manufacture stainless steel,
contributed Rp 210.41 billion to sales in 1997
compared to Rp 171.21 billion in 1996, an increase
of Rp 39.20 billion. The downward average dollar
price of ferronickel at LME, was more than offset by
Rupiah depreciation.
The
Company’s production of ferronickel is exported to
stainless steel manufacturers in Europe, South Korea
, Taiwan and Japan. Major customers of FeNi sinclude
Krupp Thyssen nirosta GmBH – Germany, Pohang Iron
and Steel Co. – South Korea, Yieh United Steel
Corp. – Taiwan, Nikkinko Trading Co.Ltd. and
Nippon Yakin Kogyo Co.Ltd – Japan.
Gold
and Silver
In
1997, gold prices reached their lowest levels in a
decade, aggravated by a market perception of large
gold sales by central banks.
Aneka
Tambang’s gold sales rose by Rp 8.55 billion from
Rp 53.25 billion in 1996 to Rp 61.79 billion in 1997
due to higher volume, from 1,805 kg in 1996 to 2,002
kg in 1997. As local gold sales are quoted at the
current exchange rate at the time of transaction,
Rupiah depreciation was the other contributing
factor to increase sales in 1997.
Sales
of silver have also increased from Rp 14.82 billion
in 1996 to Rp 15.22 billion in 1997 due mainly to
the depreciation of the Rupiah, partially offset by
a decrease in sales price from US$ 4.83/oz in 1997.
Logam
Mulia’s income increased from Rp 5.75 billion in
1996 to Rp 8.13 billion in 1997. This increase was
derived from an increase in refining services to
third parties.
On
July 24th, 1997, the Company signed a
technical consultancy agreement with Western
Australia Mint Company to review ways of enhancing
the operating performance of refining services.
NON-CORE
PRODUCTS
Bauxite
The
major customers for the Company’s bauxite include
Sumitomo Chemicals Co.Ltd., Nippon Light metal
Co.Ltd., Showa denko K.K. of Japan and Shandong
Aluminum Corporation of China.
Bauxite
sales increased from Rp 18.77 billion in 1996 to Rp
28.50 billion in 1997, due to an increase in
quantity sold from 750,911 wmt to 793,056 wmt, and
an increase in average selling price from US$ 10.74/wmt
in 1997. Increased sales other contributing factor
was the depreciation of rupiah to US dollar.
Iron
Sand
The
continuous growth of Indonesia’s infrastructure
projects resulted in increased sales from Rp 10.59
billion in 1996 to Rp 14.03 billion in 1997. Sales
volume increased from 391,185 tonnes in 1996 to
391,185 tonnes in 1997. The price of iron sand per
ton in Rupiah alsa increased from Rp 27,080/tonnes
in 1996 to Rp 29,856/tonnes in 1997.
Aneka
Tambang’s buyers of iron sand include PT
Indocement Tunggal Prakarsa, PT Semen Padang and PT
Semen Gresik.
Marketing
Plan
The
Company’s plan for nickel ore is to increase sales
volume to Japanese Smelters, Australian QNI and
other foreign buyers. For ferronickel, Aneka Tambang
will maintain in sales with the present buyers, at
the reduced scale since the relining of FeNi I was
result in reduced production in 1998 compared to
1997.
The
Company sold gold domestically at prevailing current
exchange rates of Rupiah/US dollar. The downward
movement of the Rupiah from July to December of 1997
has benefited the Company in terms of increased
revenues. However, the economic slump affecting
Indonesia has affected the domestic demand for the
year 1998. In response, the Company plans to
diversity its market base and to sell gold
internationally, particularly to Singapore.
Bauxite
will be sold to Sumitomo Chemicals Co.Ltd., Nippon
Light Metal Co.Ltd., Showa Denko K.K. of Japan.
While the contract with Shandong Aluminum
Corporation of China will be renewed by April or May
1998.
The
Company forsees a slowdown in domestic demand for
iron sand as a result of the monetary crisis. Since
Aneka Tambang only sell its iron sand domestically,
the Company is exploring opportunities of
diversifying its market.
FINANCIAL
REVIEW
CURRENT
YEAR ACHIEVEMENTS
Sales
In
1997, approximately 95 percent of Aneka Tambang’s
KP sales was denominated in US dollars, consisting
of 79 percent export sales and 16 percent local
sales denominated local sales in US dollars. Sales
for the year totalled Rp 449.56 billion, 25 percent
higher than sales of Rp 358.56 billion in 1996.
Total rupiah sales increased primarily as a result
of the currency depreciation, and a slight volume
increase. This was partially offset by a decrease of
in average selling prices of core products.
Cost
of Goods Sold and Gross Profit
The
cost of goods sold aggregated Rp 252.28 billion in
1997, reflecting an increase of 8 percent from Rp
234,02 billion in 1996. This increase was
principally due to the increased cost of production,
owing the employees’s bonus and the replacement of
power plant fuel in Pomalaa, from Marine Fuel Oil (MFO)
to Industrial Diesel Oil (IDO). The Comparative Cost
of Goods Sold to sales decrease by 10 percent from
66 percent in 1997. Aneka Tambang’s gross profit
of Rp 197.27 billion in 1997 was 58 percent higher
than the comparative amount of Rp 124.54 billion in
1996.
Operating
Expenses and Operating Income
Operating
income for 1997 amounted to Rp 146.17 billion, 66
percent higher than the previous year. The company’s
operating expenses increased by 39 percent from Rp
36.72 percent in 1996 to Rp 51.10 billion in 1997.
The increase is attributed to increased exploration
cost, and higher selling expenses which are in US
dollars.
Other
Income / Charges
The
net of other charges for the year totalled Rp 65.22
billion, an increase of Rp 13.94 billion over the
previous year of Rp 51.28 billion. The increase was
caused primarily by the loss of foreign exchange
amounting to Rp 35.20 billion, resulting from the
Company’s bank loans denominated in US dollar.
Partially offseting this, was a decrease in interest
expense, from Rp 50.54 billion to Rp 30.39 billion.
Profit
before Provision for Income Tax, Provision for
Income Tax and Net Income
Profit
before tax amounting to Rp 80.95 billion in 1997,
was up by 122 percent from Rp 36.54 billion 1996.
Provision for income tax for 1997 amounted to Rp
11.31 billion due to the negative fiscal corrections
for depreciation and share issuance cost. Net income
for 1997, amounting to Rp 69.52 billion, doubled by
113 percent from the previous year.
Privatisation
The
Company was partially privatised in 1997 with the
sale of 35 percent of the Company to new investors
and listing on the Jakarta Stock exchange (JSX) and
Surabaya Stock Exchanger (SSX). The privatisation
involved the issue of new shares, in which Aneka
Tambang raised net proceeds Rp 561.70 billion.
Dividend
Policy
The
Company’s dividend policy stipulates that payment
of each financial years dibursement shall be paid in
the second quarter of the following year. In
addition, yearly dividends payable will be a minimum
of 30 percent of the Company’s net income after
tax is decided at the Annual General Meeting of
Shareholders.
Acquisition
of ERI Ventures Inc.
On 30th
July, 1997, the Company completed a reverse taheover
of ERI Ventures Inc. (ERI), a listed Canadian
mineral exploration company. As a result of the
acquisition, Aneka Tambang has an interest of 82
percent of the 97 million outstanding shares of ERI.
After
the takeover, ERI’s corporate name was changed to
Antam Resources International Ltd. (ARI). ERI’s
interests in minerals properties in Indonesia are
held through its Indonesian opertaing subsidiary, PT
Antam Resourcindo.
Financing
Cash
and cost equivalents increased from Rp 5.56 billion
as of December 31st, 1996, to Rp 536.04
billion as of December 31st, 1997, due to
net proceeds received from the Public Offering.
The
short-term dolar denominated loans provided by ABN
Amro Bank N.V. and PT Bank Dagang negara were used
for fiancing working capital requirements. Total
short-term loans amounted to Rp 54.45 billion and Rp
139.52 billion as of year-end 1996 and 1997,
respectively The increase in obligation was caused
by the depreciation of the Rupiah against US dollar.
The
Company’s long term loans include current maturing
obligations amounting to Rp 306.95 bullion and Rp
244.44 bullion as of December 31st, 1 996
and 1997 respectively. Payments were made by Aneka
Tambang to PT Bank Dagang Negara, PT Peregrine Sewu
Securities and to Deutsche Bank AG. In Addition, the
Company obtained the Gold Project Facility amounting
to Rp 182.57 billion (relating to 135,764.5 oz of
gold), to finance the expansion of Pongkor gold
mine.
Monetary
Crisis Impact
Of
Aneka Tambang’s Initial Public Offering (IPO), the
Company received total net proceeds of Rp 561.70
billion, of which US$ 32 million was denominated in
US dollars and the balance in Rupiah. Aneka Tambang
intends to use the IPO proceeds mainly for the
expansion of production facilities of Ferronickel
III estimated to cost US$ 239 million.
Furthermore,
the currency turmoil besieging Indonesia has left
Aneka Tmabng operations largely unscathed, since
most of its products are sold abroad in US dollars.
The Company’s core products nickel and gold are
both commodities whose global prices are set in US
dollars while most of the Company’s costs are in
Rupiah. Therefore, the weakening of the Rupiah
against the US dollars is expected to result in
improved profit margins.
ENVIRONMENTAL
CONCERNS
Aneka
Tambang’s environmental policy not only complies
with government regulations, but opertaes on the
philosophy that " the use of the land by Aneka
Tambang, for economic recovery of its mineral
wealth, is of a temporary nature after which, the
land should retain its original fuctionality ".
With
his philosophy, Aneka Tambang has completed
rehabilitation of 208.31 ha in 1997. The
rehabilitation program consists of leveling the
mined area where top soil is replaced with quality
soil, complemented by tree planting. Among the
rehabilitated areas were 132 ha in Kijang Bauxite
Mine which is nearing its depletion.
Aneka
Tambang’s strong strong sense of environmental
concern has been exhibited through its enggagement
of an independent international consultancy group,
to conduct a full envronmental audit in 1997.
Aneka
Tambang’s environmental Policy stipulate that
Aneka Tambang is :
- to minmise any
long term degradation of land
- to allow for a
beneficial post mining land use
- not to have any
significant off site effects during mining
- to minimise effect
on the local community during and after mining
- not to create a
liability for future generations
The
management and employees of Aneka Tambang and all
contractors employeed by PT Aneka Tambang agree to
comply with the PT Aneka Tambang Environmental
Policy.
Aneka
Tambang has also implemented an Environmental Action
Plan. The action plan was designed to address the
identified issues at each operating unit, stating
the progress of the action taken from the issues. A
separate plan task force, consisting of key
personnel from the various operating units is
responsible for the implementation of the required
actions and for achieving the action plan schedule.
Some
of the action plans from the issues completed during
the year 1997 by various operating units are :
Kijang
Kijang
tailings dams are rehabilitated with the total
taoling storage space of 106,000 cubic meters to
limit the spillways and discharge of tailings
Pomalaa
Improvement
of waste handling was completed with the
construction of a new scrapyard and the individual
sheltered pits for disposal of asbestos and
incinerated hospital waste.
Pongkor
Construction
of the settling ponds to deposit the mud from the
mine site, so that the water will flow to the river
is clear. Waste rock location disposal is also
constructed to discharge rock from the mine.
Gebe
Construction
of 4 sediment control structures to retain the flow
of mud from the mine to the sea.
Cilacap
Former
mine site was transformed to rice fields of 2.3 ha.
SOCIAL
RESPONSIBILITIES
Social
Activities
Aneka
Tambang has continuous socially conscious programs
such as, employing the people living close to the
mining areas, granting elementary education
scholarships for employees children and introducing
family planning programs. In addition, Dharma Wanita
provides literacy programs for the local community.
In
line with the government regulations regarding
assistance for samall-size entrepreneurs and
cooperatives, during 1997, the Company spent a total
of Rp 1.23 billion of its profits for these
programs. Of this amount, Rp 0.9 billion was
allocated to assist 61 small-size entrepreneurs and
Rp 0.33 billion was allocated for the cooperatives
development. The fund was distributed in the form of
working capital loans and donations for promotional
activities and other training activities to teach
entrepreneural, managerial and technical production
skills.
Employee’s
Welfare
The
Company recognises that employee’s welfare is a
strong contribution factor to meet the Company
mission, thus, efforts have been made to improve the
welfare of all employees.
Besides
paying sufficient salaries for employees to support
their families, the Company also grants benefits
such as transportation allowances, social insurance,
healthcare benefits, work uniform, housing
allowances, sports and religious facilities.
In
addition, subsidies to all units cooperatives are
made for the benefit of the employees. The Company
also provides pension plans, organised by Dana
Pensiun Aneka Tambang, based on UU No.12, 1992. On
july 15th, 1997, the Indonesian Ministry
of Finance adopted UU No.12, 1992 as a
constitutional law, concerning the implementation of
pension programs. The Indonesian Labor regulations,
as stipulated by the Indonesian Ministry of Labor
dated March 24th, 1997, has been adopted
by the Company.
In
1997, the Company established a voluntary early
retirement program for 175 employees from 47 to 54
years old, allocating Rp 2.02 billion for this
program. Those early retired employees are still
eligible for monthly pension and healthcare
benefits. In addition, during 1997 Haj season, the
Company granted Haj allowances to 10 employees
(below head division level) who have worked for the
Company at least 10 years.
Training
programs are provided in order to develop employees
skills for their current work and future careers.
Training programs are categorised into four groups :
General Management, Vision Upgrade, Capability
Upgrade and Special Programs to prepare candidates
for leadership succession.
Safety
Program
A
vigorous safety campaign waspursued throughout the
year, resulting in a decrease in the frequency rate
of accidents per million man-hours from 1.25 in 1996
to 1.07 in 1997.
An
line with the safety program, the Company appointed
London Mining and Mineral Consultants Ltd. in
association with Steffen Robertson Kristen (UK) Ltd.
to conduct an initial audit an Pongkor Mine Safety
Program. The purpose of the audit was to improve
Pongkor’s safety program in terms of its
ocuppational and safety training, use of resources
(correct tools/equipment) and maintenance of plant
and machinery) and strategic safety plan.
Aside
from the intensive Safety Program, Aneka Tambang has
a comprehensive Company Policy on Safety Program
which include :
- Safety patrol,
done on weekly basis
- Safety Comitee
meetings done on a monthly basis to address the
issue of th employees safeness while at work
- Setting up
Standard operating procedures
- Safety programs
and training courses are conducted on a regular
basis
- Inspection by the
government agency performed on a quarterly basis
For
the year 1997, the Company showed a remarkable
record, to the extend that Kijang extend a Zero
Accident Award from the Government of the Republic
of Indonesia. Despite greater efforts and safety
programs, it is with great regret that because of of
landslides, twopeople working for contractors died
at Pongkor operations during the year – Tholib and
Badrudin – and one Aneka Tambang employee drowned
in Cilacap – Kodiarto. The management of Aneka
Tambang extends its sympathy and condolences to the
families, friends and colleagues of those who died.
COMPANY
FUTURE PLANS
Aneka
Tambang has determined that in order to become a
worls class miner, it is required to improve its
efficiency and maintain its growth level. Therefore,
the Company sets its Corporate Strategy as follows :
Focus
on Core Products
The
Company has extensive experience in mining nickel
and gold. However, since the price of these metals
is determined by market mechanism in which the
Company has no control, the Company focus becomes
productivity and efficiency.
By
expanding Pongkor, replacing and modifying FeNi I,
developing FeNi III, adding a chlorinating process
in Logam Mulia smelting and refinery and modifying
gold mining techniques, the Company intends to
increase its production capacity, which should
decrease production costs. Hence, Aneka Tambang
gains the necessary competitive advantages to
compete with its international peers.
Increase
of Exploration activities
Mines
are unrenewable resources. Thus, the Company needs
to conduct continuous exploration activities in new
areas with potential deposits. The company realises
that exploration activities are important for
supporting the Company’s existence in the future.
In line with this, Aneka Tambang has significally
increased its exploration budget to 5 percent of
annual sales. The Company’s 73 KP’s cover mining
area for 5.3 million ha., promising additional large
finds.
Aneka
Tambang is conducting exploration zctivities either
independently, through its subsidiaries or in joint
ventures with partners.
Strategic
Alliances
In
making joint ventures with strategic partners, the
Company benefits from capital inflows, technology
transfer and management expertise. Currently, Aneka
Tambang has joint ventures with international mining
companies such as BHP, QNI, Aberfoyle, Newcrest and
Ashton.
Although
most of the joint ventures are still at the
exploration stage, some have reached feasibility
study stage, such as the Gag Island Poject with BHP,
the Gosowong gold project with Newcrest and the
alluvial diamond deposits in South Kalimantan with
Ashton – MMC. In the future, Aneka Tambang will
continue to seek strategic alliance to explore
potential mineral deposits on existing areas.
Corporate
Reorganisation
To
improve the Company’s performance, the Company
recognises that it must meet efficiency and
professionalism needs in line with modern business
practises. The Company restructuring plan of
dividing its businesses into four primary opertaing
divisions of nickel, gold, industrial minerals and
geological division entails profit accountability
for its division resulting in improved efficiencies. |